|
Pact
Sought on Pile Driving Near P.S. 234
By Etta Sanders
Just as P.S. 234 students were getting ready to start the new school year,
City Councilman Alan Gerson was working to hammer out an agreement with
developers to avoid months of ear-splitting pile driving directly across
the street from the school.
Construction of a residential and
retail complex on Site 5B, the lot bordered
by Warren, Greenwich, Murray
and West Streets, is slated to begin this
fall.
The planned sale of the city-owned
property is scheduled to come before a
Council committee for a vote on Sept.
7, with a final Council vote likely to
take place two weeks later. But Gerson
said that unless there is an adequate
noise-abatement agreement, in writing,
the Council will vote against the application.
"We've made it clear that we'll turn
it down if they don't have a noise
plan," he said. "We're not going to put
up with three months of noisy construction
work during school hours."
The parties made some progress by
the end of last month. After testing the
ground in the spring, the project's
developer, Minskoff Equities, had said
that it would need to drive 1,200 piles
over 12 weeks. By exploring alternatives,
including larger piles, they were
able to reduce that number by half, to
600 piles over eight weeks, according
to Gerson's office. One of those weeks,
they agreed, will be during Christmas
break when school is out. The work
could begin in October.
Additionally, Minskoff has agreed
to construct a sound barrier along the
south side of Warren Street, which
would reduce the decibel level from 90
to 80, or a 50 percent reduction,
according to Gerson.
But school and community officials
say they are not sure that is enough.
"We're trying to determine what an
acceptable noise level should be," said
Sandy Bridges, the principal of P.S.
234. "I don't know what 80 decibels
sounds like."
The PTA is planning to hire an
independent noise consultant with its
own funds, but the money cannot be
allocated until parents meet after the
school year begins. Gerson said they
will have a consultant in place in time
to work out a final agreement.
With 65 school windows directly
facing the site, Bridges said, it's critical
that classroom time not be disrupted.
"It's time that can never be regained.
I've got testing in January. If I'm going
to have brain-numbing pile driving
[before then], that just doesn't make
any sense. It will make it too hard for
the kids. Workers have to protect their
ears, but you can't put ear plugs on all
the kids."
Under an agreement between Gerson
and the city, the developer must
use "community-friendly" procedures
as a condition of the land sale. The
goal, Gerson said, is for construction
on the Site 5B project to be no more
disruptive than work done last spring
by Resnick & Sons on Site 5C, the lot
behind the school. That project used a
quieter method for pile driving.
Community Board 1 sent a letter to
Minskoff suggesting that the work
schedule be shifted to start at 1 p.m.
and end at 9 p.m., and offered to work
with the trade unions on making those
accommodations. That would limit the
amount of pile driving during the
school day, from 8:30 a.m. to 3 p.m.,
but may not be acceptable to nearby
residents.
Some parents at the school feel
there is no amount of pile driving that
would be acceptable during school
hours. John Jiler, who heads a parents'
construction committee, said many of
the school's more than 700 families
will participate in a demonstration near
the site if the construction impairs
learning.
The real issue is money, he said.
"This is easily doable outside of school
hours if Minskoff was willing to pay."
The noise abatement could add as
much as $2 million to the construction
costs, according to Gerson's office.
Those costs may be negotiated as part
of the sale of the property. "It might
involve extra money," said Gerson,
"but that pales in comparison to subjecting
children to three months of
excessive noise."
A spokeswoman for Minskoff Equities
said the developer would not
comment until an agreement had been
reached.
|